A blank canvas.
Container workshop footing digout.
Container workshop footing digout.
Container workshop wall steel.
Footing for container workshop brick wall
Brickies hard at it.
The container workshop wall finally finished
Musical containers.
Container 1
Container 2
Container workshop.
Roof frame on container workshop.
Power cables in.
Office/toilet block digout.
Office/toilet block digout with compact.
Boxing in for office/toilet block
Fresh concrete footings for office/toilet block.
Boxing removed from office/toilet block footings.
Office/toilet block footings and small fire wall done.
Office floor joists in.
Toilet block finally has a floor.
Framing and cladding of office/toilet block.
Office block not far from having a roof.
Back of the toilet block
Ever reliable Kubota U15-3
Prepping for the office/toilet block deck.
More services…
And more services…
A happy sight to see your toilet flush for the first time.
Our 5t tipper taking another load off to Lyttelton.
Some of the approx 250m of 150mm concrete being cleared.
Just a small amount of the concrete removed from site.
Just a piece of the three 25m long concrete beams removed from site.
All concrete removed and ready for machinery shed digout.
Machinery shed digout.
Bloody rain.
The way ECan like to see spoil stored.
Machinery shed footing ready for concrete
Concrete pump.
Boxing off the machinery shed footing showing some fresh concrete
Boxing off machinery shed footing.
Machinery shed footing.
View of machinery shed footings backfilled and mark out of office/toilet block deck piles.
Machinery shed footing
Texco erecting the machinery shed steel.
The machinery shed steel finally in – Texco did the job
View of office/toilet block deck with access ramp boxed and ready for pour.
Our Komatsu PC14R having a clean up.
Finally get our gear in one place in the machinery shed.
Glorious lighting!
The yard pretty much as it is today.